1. Warm Electronics:  1/2/06 – 12/31/09
    1. Design and Prototype: 1/2/06 – 6/30/08
      Goal:  Have ~10 boards useful for test stands with ability to trigger and save events to standard CDMS file format, with data useful for analysis.

                                                               i.      V1 design, building and testing:  1/2/06 – 1/8/08

                                                             ii.      V2 design, order 2-4 circuit boards:  11/1/07 – 1/8/08
Expect to be close to final version

                                                            iii.      V2 assembly and initial testing of 2 boards:  1/8/08 – 2/8/08

                                                           iv.      V2 order and assembly of 8 boards:  2/8/08 – 6/30/08

                                                             v.      V2 testing with test-stands:  2/8/08 – 9/30/08

    1. Design and prototyping of final version:  4/1/08 – 12/31/08
    2. Design production testing process:  4/1/08 – 12/31/08

                                                               i.      Develop checklist to certify board

                                                             ii.      Design and produce jig for testing and DAC calibrations

    1. Production and testing of full set of cards:  1/1/09 – 12/31/09
    2. Design and produce QET Isolator boards:  9/1/08 – 3/31/09
    3. Design and produce FEDUP boards:  9/1/08 – 6/31/09
  1. DAQ:  1/2/06 – 12/31/10
    1. Specifications:  7/02/07 – 1/31/08
    2. Specifications for monitoring:  1/31/08 – 2/31/08
    3. Development of basic Labview control:  1/1/07 – 2/8/08
    4. Select and implement version control for labview Vis:  1/8/08 – 3/31/08
    5. Development of DAQ for test facilities:  1/8/08 – 6/30/08

                                                               i.      Incorporate DCRC control into ZIPFEBmodular Vis

                                                             ii.      Incorporate DCRC control into DarkScript and LightEvent

                                                            iii.      Interface DCRC to CDMS data file format.

                                                           iv.      Implement global trigger and readout for multiple detectors

    1. Design final version for experiment:  7/1/08 – 12/31/08
    2. Design monitoring system for experiment:  7/1/08 – 12/31/08
    3. Develop version for systems test:  1/1/09 – 6/1/09
    4. Develop final version for experiment:  6/1/09 – 12/31/10